What a permanent ice rink is
It is a real ice rink that stays installed and opens all year round, in any climate. It is designed for continuous commercial operation: public skating sessions, a skating school, birthday parties, events and, if the size allows, hockey training.
We design it to fit the building or site, in any dimensions and in non-rectangular shapes too. If you are after something out of the ordinary, take a look at our custom-shape ice rinks.
Fixed or semi-permanent rink
There are two ways to build a permanent rink:
| Fixed rink | Semi-permanent rink | |
|---|---|---|
| Base | Pipework under special concrete in professional 30 x 60 m rinks; no concrete in the rest | Cooling floor on the existing surface |
| Installation | 5 to 7 days without concrete; up to 30 days plus curing with concrete | 5 to 7 days |
| Dismantling | Difficult | A few days |
| Service life | Over 15 years | About 15 years |
| Cooling system | The same | The same |
If the fixed rink has no concrete, there is no curing time and it is installed in about the same time as a semi-permanent one. The semi-permanent rink is the most flexible option for shopping centres or leased premises, because the investment is not tied to the building.
Why our floor does not leak
On a rink that runs 365 days a year, a floor failure is expensive. Many rinks on the market use rubber mats that get punctured and lose coolant, with manifolds in a header that cools the air. We do it differently:
- 2 mm wall tempered aluminium pipework, with no risk of punctures.
- Manifolds inside the ice itself and only two insulated pipes running to the machinery.
- Insulating board under the cooling floor, so the cold goes up into the ice.
- Double insulation, so no water escapes beyond the barriers and no damp condenses underneath.
- Propylene glycol as the circuit coolant.
This means rinks can be installed on a roof terrace, above a car park or on a shopping centre floor with units below. More detail on our freezing system.
Machinery built to run all year
The chiller is the heart of the rink. We do not adapt air conditioning units: we build our own ice rink chillers in three models (VN060, VN125 and VN180). They have two hydraulic pumps that a computer alternates to spread the wear; if one fails, the other keeps the rink running. See ice rink machinery.
The machinery is installed outside, as close to the rink as possible. Set aside about 35 m² for it. When it has to be further away, we add extra insulation to the pipework so no energy is lost along the way.
Daily ice maintenance
Skating creates snow on the surface. It has to be removed and a very thin film of hot water laid down to cover the marks. On small rinks this is done by hand with special shovels; rinks over 300 m² benefit from an ice resurfacer, and rinks over 1,500 m² need a professional-size resurfacer. The edges along the barriers need special attention so that no steps form. See ice maintenance.
Equipment to run the rink
A permanent rink needs more than ice: hire skates in every size, lockers to store them (each holds 20 pairs), skating aids for children, helmets and barriers that suit the venue’s interior. We supply all of it; see ice rink accessories.
Think about the business around the rink as well. A bar with tables by the ice, glove sales, birthday parties with exclusive use of the rink and monthly passes all generate revenue on top of ticket sales. You can estimate your figures with the ice rink profitability calculator.
How to get started
Manufacturing takes 12 to 14 weeks from the moment the design is signed off. We start with the space: dimensions, access, where the machinery and changing area will go. We send you a layout, then a render and a fixed quote. See the purchase terms on ice rinks for sale or request your quote.